Project Description: Construction of three (3) bentonite and HDPE lined liquid hazardous waste impoundments at Borger, Texas Complex. Construction included removing overburden and an extensive layer of rock; constructing containment berms; placing a three-foot (3′) bentonite enhanced clay liner (26,850 cu yds); and installing a 100-mil HDPE liner, a leak detection system, and a 60-mil HDPE cover liner. A total of 216,780 cubic yards was cut from construction and borrow areas, and 89,950 cubic yards of fill was used.

Contract Value: $4,158,000
Project Duration: 6 months